摘要:If,under the shuipbuilding contract,the respondent-shipbuilder is not entitled to dispose of a ship under construction,a dammage,suffered by the respondent because of ordering the provisional measure of the prohibition of the alienation or other kind of disposal of the ship under construction,is only slight. In that case,an applicant must not show the existence of a danger that without such provisional measure the respondent will make it impossible or very difficult to obtain payment. The probability of the existence of the applicant's claim is primarily considering under the shipbuilding contract.
其他摘要:Ako protivnik osiguranja-brodograditelj,prema ugovoru o gradnji broda,nije ovlašten raspolagati brodom,šteta koju on trpi zbog određivanja privremene mjere zabrane otuđenja ili drugog raspolaganja brodom u gradnji je neznatna,U tom slučaju predlagatelj os